tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2022
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Bertha resumes tunnelling as WSDOT counts the cost

Bertha resumes tunnelling as WSDOT counts the cost

Tris Thomas

Written by Tris Thomas on 25/07/2016 in News

Tagged:

Seattle’s Alaskan Way Viaduct Replacement Program contractor, Seattle Tunnel Partners JV, resumed mining on July 18th following a month of routine and hyperbaric maintenance on Bertha, the 57.5ft diameter Hitachi Zosen EPBM being used to bore the 2.7km long road tunnel. The move has allowed Client, the Washington State Department of Transportation (WSDOT), to review and publish the program and cost implications for the entire project.

Crews inspected and repaired machine components as needed during the maintenance period, which started on June 23.

The maintenance period included more than 40 shifts of work under hyperbaric conditions, changing cutting tools and performing other maintenance behind the cutterhead. In all, STP changed 33 of more than 700 cutting tools.

Tunnel boring is now one-third complete. The machine is located approximately 120 feet beneath Spring Street, tunnelling north toward First Avenue. At its deepest point near Virginia Street, the machine will be more than 200 feet below the surface.

STP expects to stop two more times for maintenance before reaching the future north portal, near the Space Needle.

After resuming tunnelling, STP updated their schedule, allowing WSDOT to do a preliminary review of the overall program schedule and budget.

The tunnel project is delayed, which has led to additional WSDOT costs, including for contract administration and oversight, says WSDOT in a project update. The costs to acquire right of way along the tunnel alignment have also been higher than originally projected, in part because of the need to extend agreements and leases. Upcoming construction projects, such as demolishing the viaduct, will have additional costs due to the tunnelling delay.

The legislatively-approved budget for the program is $3.1bn. Based on a preliminary review, WSDOT anticipates a 1.8 percent budget increase, or a cash-flow need of up to $60M in the 2017-2019 biennium, to ensure continued progress.

Looking toward completion of the viaduct replacement program, WSDOT says it estimates a total provisional budget need of $223M. That reflects a potential increase of 6.6 percent. These are preliminary estimates and WSDOT will continue to refine them as work progresses.

WSDOT has notified the Washington State Legislature of the program’s cash flow needs for the 2017-2019 budget cycle and will work with the Legislature through the budgeting process. The immediate focus according to WSDOT is addressing the up to $60M needed as a result of the tunnelling delay. The next 18 months of construction will tell a great deal about the program’s funding needs beyond the current biennium.

“We remain committed to completing this important safety project while also protecting taxpayers,” said Roger Millar, Acting Transportation Secretary, “We will continue to follow the terms of the design-build contract to recover the added costs that are due to the delay of the project.”

This includes pursuing insurance claims, identifying potential cost savings in other elements of the program and ongoing litigation to recover damages. If efforts to recover costs are successful, the funds would likely not be available until after the project is complete.

WSDOT will continue to provide additional details about the program’s budget needs as the 2017 legislative session approaches. In the meantime, the focus, according to WSDOT, will remain where it always has: on delivering the tunnel and replacing the Alaskan Way Viaduct for the people of Washington.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

05/08/2022

Big Tex’s landmark breakthrough after diameter change

Big Tex’s landmark breakthrough after diameter change

On July 25, 2022, ‘Big Tex’ a Robbins Main Beam TBM successfully broke through in Dallas, Texas, USA on the…

28/11/2022

Lower Thames Crossing plans accepted for examination

Lower Thames Crossing plans accepted for examination

The UK Government’s independent planning authority, the Planning Inspectorate, has confirmed it has accepted National Highway’s application for a Development…

19/12/2022

hyperTunnel sign MoU with University of Birmingham

hyperTunnel sign MoU with University of Birmingham

hyperTunnel, a British technology company innovating underground construction, and the University of Birmingham have signed a Memorandum of Understanding (MoU)…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more