tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2022
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Black River double shield launches in Ohio

Black River double shield launches in Ohio

Amanda Foley

Written by Amanda Foley on 16/12/2013 in News

Tagged:

Near the banks of the Black River, a 7m (23ft) diameter Robbins Double Shield TBM and continuous conveyor system are starting up.   The mammoth machine was built using Onsite First Time Assembly (OFTA), a Robbins-developed method that saves contractors in shipping time, costs, and man-hours worked.

Using the OFTA approach, individual systems are tested prior to delivery but the machine is never fully assembled in the shop. Robbins field service technicians work on location with the contractor to assemble the machine and provide support. Launch for the 1.6km (1-mile) Black River Tunnel took place on November 18th, approximately three months after assembly began.

“OFTA was a challenging process for everyone onsite. We had to make numerous adjustments. Regardless, our team worked diligently to overcome challenges, and we were able to get the TBM assembled and launched relatively close to schedule,” said Mike Garbeth, Project Manager for Wisconsin-based contractor Super Excavators, Inc. In addition to the TBM, Robbins has supplied an in-tunnel continuous conveyor system and space-saving J-type vertical conveyor.

The Double Shield machine will be used in a unique manner as it bores. “We’re expecting decent production with minimal cutter wear, as the drive is in a softer shale. We are installing ring beams and lagging, and there will be a final monolithic pour after tunnel completion,” said Gregg Rehak, Tunnel Supervisor for Super Excavators. Rather than concrete segments, ring beams are being erected within the tail shield for installation as the machine passes.

As of early December, the machine has advanced approximately 60m (200ft) into the bore. “Tunneling started a bit slow while we made final adjustments to the TBM and conveyor assembly, but mining has picked up and we are beginning to reach anticipated production rates,” said Garbeth.

The major components of the Black River Tunnel include the launch shaft and reception shaft – approximately 11m (36ft) in diameter and 50m (165ft) deep – and a 1.7km (1-mile) tunnel with a finished diameter of 5.8m (19ft). Ric-Man Construction was subcontracted to build the shafts.

The project route runs along city property roughly parallel to the Black River, beginning at the launch shaft near the Black River Wharf and terminating near the Lorain Black River Wastewater Treatment Plant. A screening facility will be built at one end near the wastewater treatment plant, where water will be diverted into the storage tunnel, and a pump station will be constructed at the launch shaft site. When complete, the pump station will move water from the storage tunnel back into an existing sewer interceptor.

Mining is expected to be completed by spring 2014 and final project completion is set for 2015. When finished, the tunnel will have a storage capacity of 42 million litres (11 million gallons) per day, providing a significant boost in water quality for the city of Lorain.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

11/05/2022

Normet to acquire Aliva Equipment from Sika

Normet to acquire Aliva Equipment from Sika

Normet has entered into an agreement with Sika to acquire its Aliva Equipment business assets. With the acquisition, Normet supports…

27/01/2022

WTC2022 Copenhagen postponed to September

WTC2022 Copenhagen postponed to September

The WTC2022 Organizing Committee and the ITA have announced that the WTC 2022 in Copenhagen has been postponed and will now…

06/05/2022

Diggy Stardust prepared for launch on Scarborough Subway Extension

Diggy Stardust prepared for launch on Scarborough Subway Extension

Ontario’s Metrolinx is marking another important milestone for its three-stop Scarborough Subway Extension as the project’s 11.9m diameter Herrenknecht TBM,…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more