Contractor Italian-Thai Development PCL (ITD) has recently celebrated the breakthrough of its 6.39m diameter S70 EPB Terratec TBM on one of three underground civil works contracts for the first 23km-long (East Section) phase of the Mass Rapid Transit Authority of Thailand’s (MRTA) Orange Line Project. The Westbound tunnel breakthrough on Contract E3 took place a full month ahead of schedule putting the project on a good footing for the upcoming Eastbound tunnel drive.
Contract E3, which was awarded to ITD in May 2017, totals over 6km of TBM driven tunnel and three underground stations, extending from Hua Mak to Khlong Ban Ma. The S70 machine began mining westwards from the Khlong Ban Ma station box on January 12, 2019, and quickly got up to speed following its initial drive. By late-March, the TBM was achieving progress rates of up to 18 rings per day and had already undertaken its first intermediate breakthrough. July 2019 marked the TBM’s best month of progress, achieving a total advance of 663.4m and a best day of 40.6m.
The machine was designed to tackle the variable soft ground geology of the city – which ranges from soft and medium to stiff and very stiff clays, with lenses of dense sand and the potential for high pressure groundwater inflows – as well as the need to mine through numerous diaphragm wall shafts and, potentially, concrete piles.
“Due to extensive project planning we were well prepared for the 3.3km long drive and any challenges had pretty much been solved on paper before the TBM commenced.” says Bunjerd Emnuch, TERRATEC’s Tunnel Manager. “The only remaining challenge was obstruction cutting. The TBM had to cut through 10 diaphragm wall panels during break ins and break outs with only two cutterhead interventions.”
The TBM’s soft ground cutterhead features a spoke style and the addition of back-loading knife bits to assist break-in and break-out of the shafts. In addition, the machine is fitted with an active bentonite face support injection system and double gated screw, to ensure face stability and mitigate settlement during excavation in areas of flowing sands and high groundwater pressure.
As the machine progresses along the alignment, it has been installing a precast concrete segmental lining consisting of five x 1200mm wide Universal style segments plus key, with an internal diameter of 5.7m.
In total, TBM tunnelling operations for ITD’s Orange Line (East) contract are expected to last approximately two years.
The S70 TBM is now being prepared for Contract E3’s 3.3km long Eastbound tunnel drive and is currently expected to relaunch next month.
Bangkok’s new Orange Line will eventually total about 35.4km with 26.2km aligned underground with 23 underground stations and another 9km and seven stations on elevated structures. When complete, in 2023, the Orange Line will provide a vital transportation link from Bangkok’s city centre to districts in the east, reducing traffic congestion and paving the way for improved accessibility, economic growth and new residential and commercial opportunities along the alignment.
Terratec
Incorporated 30 years ago, TERRATEC is one of the world’s leading designers and manufacturers of Tunnel Boring Machines, encompassing all...
More Information | info@terratec.co | +852 3169 3660
Comments: