tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Canadian Tunnelling
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2024
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Contract CC-34 completion in Delhi

Contract CC-34 completion in Delhi

Written by Tris Thomas on 30/09/2015 in News

Tagged:

Late August saw the breakthrough of the TERRATEC TBM S36 at Palam Station, 27 days after its twin S37 did the same, completing the last drives on Contract CC-34 of Delhi Metro Phase-III.

With this, the Contractor, a Joint Venture of Hindustan Construction Company Ltd. of India and Samsung Engineering & Construction Group of Korea, has bored a total of 3.6km by using TERRATEC TBMs.

The breakthrough ceremony was held in presence of the Project Owner, Delhi Metro Railway Corporation, and the Contractor, . “We are thankful to all our sub-contractors and equipment suppliers, especially TERRATEC, as these TBMs have excavated very smoothly and this has helped to complete the works ahead the planned schedule” Mr. Raman Kapil, JV’s Project Director, mentioned during his opening speech.

The Contractor selected TERRATEC to design and manufacture two Ø6.52m EPBMs with a traditional soil configuration, equipped with a Spoke-Type Cutter Head with a 57% opening ratio. The machines were nicknamed “Jantar” and “Mantar” to remember the Indian gigantic instrument created in the 18th Century to measure the time of the day.

The boring of the first stretch started in August 2014 from Vikaspuri Shaft and broke through near Kerala school, where a train cross-over has been planned for this Metro Line, completing a short drive of 219m. From there both TBMs were dragged 110m through the cross-over area to start boring a second drive of 354m to Janakpuri Station. On this drive, The TBMs passed beneath the existing Janakpuri elevated metro station. The distance between the tunnel wall and foundation piles of the existing metro station was only 3m.

All the stretch between Vikaspuri and Janakpuri stations were under moderate water pressures of up to 2bar. The geology was composed of very wet silty clay & sandy soil typical of Delhi. Both TBMs passed underneath residential areas keeping the settlement within less than one centimeter.

The final stretch of the project for TERRATEC TBMs went from Dashrathpuri to Palam Station. The twin 1224m long drives passed through very dry soil, for what the foam injection system on the TBM CutterHead was appropriately used for conditioning of the muck. The TBMs went beneath the Palam flyover where the distance between pillars and TBMs was less than 4m. On this last stretch, the Contractor kept steady weekly advances up to 120m per week, what allowed the tunnelling work to be completed for the original planned time.

TERRATEC has deployed a total of eight TBMs which so far have excavated over 12km of metro tunnels for different Contracts on Delhi Metro Phase III. All tunnelling works will be completed by the beginning of 2016.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

08/05/2025

Hunter Street Station excavation complete

Hunter Street Station excavation complete

A major milestone has been reached in the delivery of the Sydney Metro West project, with excavation of the Hunter…

22/01/2025

First Lesotho TBM in 20 years Breaks Ground

First Lesotho TBM in 20 years Breaks Ground

Tunnelling by the Katse TBM was launched on 15th January 2025 on the Lesotho Highlands Water Project II by the…

07/04/2025

Herrenknecht receives bauma 2025 innovation award

Herrenknecht receives bauma 2025 innovation award

Herrenknecht has kicked off the internationally renowned Trade Fair,  bauma 2025, which begins today, by being announced as the recipient…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social

Facebook Linkedin X-twitter Instagram
Youtube Soundcloud Linkedin Rounded Border Svgrepo Com White

Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.Ok