tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Canadian Tunnelling
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2024
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Hong Kong SIL(E) breakthrough

Hong Kong SIL(E) breakthrough

Written by Tris Thomas on 21/10/2014 in News

Tagged: underground

Excavation of the 3.2km Nam Fung Tunnel connecting Admiralty and Ocean Park stations on South Island Line (East) (“SIL(E)”) was successfully completed on 17 October 2014. The breakthrough marks an important step forward in the construction of the rail connection between the Southern District and the business centre on the northern part of Hong Kong Island.

Drill-and-blast excavation works for Nam Fung Tunnel commenced in August 2012 and was undertaken in a single direction from south to north with only one work front. A total of 750 blasts were carried out with 500 tonnes of explosives detonated, producing approximately 280,000 cubic metres of excavated material.

“The construction of Nam Fung Tunnel has been one of the biggest challenges of the SIL(E) project due to the difficult underground conditions along the tunnel alignment. Hundreds of construction workers, engineers and other specialists have strived hard to overcome the challenges with a view to creating the shortest route between the north and south sides of Hong Kong Island for the convenience of the community. I am most grateful to our contractor partner who has worked closely with the MTR team to complete this challenging work,” said Mr TC Chew, Projects Director of MTR Corporation.

The tunnel excavation works had to pass through Wan Chai Gap Fault Zone and Magazine Gap Fault Zone, where there were soft materials within the rock and a higher chance of water ingress into the tunnel. Additional grouting and tunnel strengthening works were therefore required. With the excavation carried out in a single direction with only one exit, careful coordination was required to manage the heavy traffic in and out of the tunnel every day to transport the spoil from the blasting while bringing in construction materials for the tunnel structures.

Taking great care to minimise the impact of the excavation works on various stakeholders and the environment, the team implemented robust noise mitigation measures, closely monitored vibrations from blasting and maintained continual communication with the local community. The contractor also enhanced the environmental measures including setting up an award- winning filtering system that recycles waste water for further use in the works site to conserve water. Moreover, the Corporation has focused on providing workers with a safe and healthy working environment.

-more-“Tunnel excavation is very tough work especially under such difficult geological conditions, so we do our best to make things easier for our workers. In addition to regular checks on air quality and the provision of adequate ventilation facilities, we also offer, for example, air-conditioned rest areas and ice cooling at work fronts to make the working environment more comfortable,” said Mr Chew.

With all tunnel excavation works and about 80 percent of the tunnel lining works for Nam Fung Tunnel completed, track-laying works and installation of trackside cables and overhead lines will commence soon.

Meanwhile, the extension works at Admiralty Station, in particular, the underpinning works of the Island Line tunnels, remains the biggest challenge in the SIL(E) project. The project team will continue to strive to complete the works as quickly as possible.

Construction of the South Island Line (East) project began in May 2011. As at the end of September 2014, more than 78 percent of the overall works has been completed. The line runs 7 kilometres from Admiralty to South Horizons with three intermediate stations at Ocean Park, Wong Chuk Hang and Lei Tung. Comprising tunnel and viaduct sections, the medium capacity railway will operate trains at a frequency of approximately 3 minutes during peak hours.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

07/04/2025

Dual-channel slurry TBM passes FAT

Dual-channel slurry TBM passes FAT

Large-diameter dual-channel slurry TBM “CREC 1503” manufactured by CREG (China Railway Engineering Equipment Group Co., Ltd.) has successfully completed its…

20/12/2024

Herrenknecht supply India’s twin largest TBMs

Herrenknecht supply India’s twin largest TBMs

Herrenknecht AG has announced it will supply two Mixshields to the prestigious Versova-Dahisar Link Road in Mumbai. At 15.62m diameter…

17/04/2025

Preferred bidder for HARP project advisor role announced

Preferred bidder for HARP project advisor role announced

Following a competitive tender process, UK client, United Utilities has announced Turner & Townsend Infrastructure Limited as the preferred bidder…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social

Facebook Linkedin X-twitter Instagram
Youtube Soundcloud Linkedin Rounded Border Svgrepo Com White

Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.Ok