The winners of the £6.6bn of major construction contracts for Britain’s HS2 have been announced today (17 July 2017). The huge infrastructure investment covers the main civil engineering work on the first phase of HS2 between London and Birmingham – including construction of tunnels, bridges, embankments and viaducts. The winning bidders to build the first phase of the route are:
Area South
- Euston Tunnels and Approaches – SCS JV (Skanska Construction UK Ltd, Costain Ltd, STRABAG AG)
- Northolt Tunnels – SCS JV (Skanska Construction UK Ltd, Costain Ltd, STRABAG AG)
Area Central
- Chiltern Tunnels and Colne Valley Viaduct – Align JV (Bouygues Travaux Publics, VolkerFitzpatrick, Sir Robert McAlpine)
- North Portal Chiltern Tunnels to Brackley – CEK JV (Carillion Construction Ltd, Eiffage Genie Civil SA, Kier Infrastructure and Overseas Ltd)
- Brackley to South Portal of Long Itchington Wood Green Tunnel – CEK JV (Carillion Construction Ltd, Eiffage Genie Civil SA, Kier Infrastructure and Overseas Ltd)
Area North
- Long Itchington Wood Green Tunnel to Delta Junction and Birmingham Spur – BBV JV (Balfour Beatty Group Ltd, VINCI Construction Grands Projets, VINCI Construction UK Ltd, VINCI Construction Terrassement)
- Delta Junction to WCML Tie-In – BBV JV (Balfour Beatty Group Ltd, VINCI Construction Grands Projets, VINCI Construction UK Ltd, VINCI Construction Terrassement)
Preparatory works are already underway, with main construction work starting in 2018/19 following a period of detailed design work.
In addition, HS2 stations at Euston, Old Oak Common and in Birmingham will be central to HS2 and the work needed to develop designs is also well underway. Both the invitations to tender (ITTs) for the station design services contracts for all 4 Phase One stations and the invitation to participate in dialogue (ITPD) for the Euston Master Development Partner have been released to shortlisted bidders.
These are significant milestones which show how progress is continuing to deliver stations that will be embraced by the local communities, drive economic growth and provide seamless journeys for passengers.
A series of other HS2 announcements are taking place today.
The Transport Secretary will today publish a Bill to deliver the next phase of HS2, from the West Midlands to the West Coast Main Line south of Crewe.
This means – subject to Parliamentary approval – this part of the route can open in 2027, 6 years earlier than planned, to bring the benefits of HS2 to the north and Scotland sooner.
The Transport Secretary will also confirm the final Phase 2b route, from Crewe to Manchester and Birmingham to the East Midlands and Leeds. This phase will complete HS2 and unlock the transformative project’s full benefits for the country.