tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2022
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Indianapolis gears up to bid Deep Rock Tunnel Connector

Indianapolis gears up to bid Deep Rock Tunnel Connector

Amanda Foley

Written by Amanda Foley on 18/04/2011 in News

Tagged:

The Indianapolis Department of Public Works is due to advertise its 7.5-mile (12.2km) Deep Rock Tunnel Connector (DRTC) project at the beginning of May. Designed by AECOM, the DRTC will be capable of conveying combined sewer overflows (CSOs) of up to 550 million gallons/day, to capture sewage from three of the city’s largest overflow locations. The 18ft (5.48m) i.d. tunnel will be bored at depths of 270ft (82m) through limestone and dolomite using a main beam TBM and lined with un-reinforced concrete.

The estimated $200-$300 million contract will include a TBM launch shaft, located at the city’s Southport Advanced Wastewater Treatment Plant, a retrieval shaft, 3 x utility shafts and 3 x vortex drop shafts. In addition, 5,600ft of levee improvements are required to protect the site from a 500-year flood event.

John Morgan, Tunnel Program Manager for Indianapolis Department of Public Works, told Tunnelling Journal that ground investigations show excellent material for tunneling, with projected high boreability and low abrasivity. “I don’t know that we could be in a better medium,” says Morgan.

Average advance rates of 100ft (30m) per day are expected on the basis of 24hr working with a 4-6hr maintenance shift. “If you match mucking rates to that, your looking at 20 to 25 trucks an hour,” says Morgan. However, 7pm-7am noise restrictions would require night time stockpiling, which would mean 50-60 trucks per hour during the day. Another possible option would be sale of the material to American Aggregates, who operate a surface mine adjacent to the Southport site. “It would be very simple to run a conveyor over to that property,” says Morgan. “But at the end of the day it’s the contractor’s decision what he does.”

The DRTC is the first phase of Indianapolis’ federally mandated Consent Decree and $1.7 billion Long Term Control Plan to curb combined sewer overflows. Four additional deep storage tunnels will also be built: The White River and Fall Creek tunnels (which will commence in 2015); and the Pleasant Run and Pogues Run tunnels (which will begin in 2020). The entire Deep Rock Tunnel System is due to be completed in 2025.

DRTC bids are scheduled for opening in July, with Notice To Proceed (NTP) expected approximately 60 days later, in September. Final completion of the project is scheduled for August 2017. At that point in time DRTC’s retrieval shaft will become the launch shaft for the White River Tunnel, which is currently at the 30% design stage by Black & Veatch.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  1. Jlscott says:
    16/03/2012 at 10:38 pm

    Is the DRT Project going to be re-bid, or is it underway already?
    Does anyone have any answers to this?  If it is scheduled to begin,
    has the construction began? 

    Reply
  2. Jimjanetmoyer says:
    19/06/2011 at 1:43 pm

    is the jobn union or not. does prevailing wage going to exist on this one and if it is union what local will they hire out of?

    Reply
  3. Amanda Foley Amanda Foley says:
    19/04/2011 at 1:50 pm

    Many thanks for your comment. Just to clarify: The project will be bid in the next few weeks. The sale of excavated tunnel muck to American Aggregates is just one of many disposal options available to the low-bidding contractor selected to perform the job. That will be the contractor's decision. It just so happens that an American Aggregates surface mine directly adjoins the launch site and we thought it noteworthy. The client has no intention of taking ownership of the excavated material or imposing any restrictions (other than the pre-existing night-time noise restrictions) on the contractor in this regard.

    Reply
  4. mendel says:
    19/04/2011 at 11:30 am

    so this is a open bid???????? Sounds like American Agg already has the job, or maybe thats just my observation. HA!

    Reply

Search

Digital Edition

More Like This

14/02/2023

Bids returned for NHSRCL 21km tunnel

Bids returned for NHSRCL 21km tunnel

India’s National High-Speed Rail Corporation Limited’s (NHSRCL) call for bids for the construction of a 21km tunnel on the Mumbai-Ahmedabad…

08/11/2022

Shortlist for Sydney Airport Metro announced

Shortlist for Sydney Airport Metro announced

Three organisations have been shortlisted to deliver key construction work on the Sydney Metro – Western Sydney Airport project. The…

06/12/2022

HS2 smashes Diesel-free sites target

HS2 smashes Diesel-free sites target

On its journey towards fully diesel-free construction sites by 2029, the UK’s HS2 project has announced that 10 sites are…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more