tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2022
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Kuala Lumpur-Singapore High Speed Rail PDPs selected

Kuala Lumpur-Singapore High Speed Rail PDPs selected

Tris Thomas

Written by Tris Thomas on 18/04/2018 in News

Tagged: Gamuda,Kuala Lumpur-Singapore High Speed Rail

Client body for the Kuala Lumpur-Singapore High Speed Rail (‘KL-SG HSR’),MyHSR Corporation Sdn Bhd (‘MyHSR Corp’), has completed its Project Delivery Partner (‘PDP’) tender and selected two consortia to assist project’s civils works portion.

The Malaysian Resources Corporation Berhad-Gamuda Berhad consortium (‘MRCB Gamuda Consortium’) has been selected for the northern portion of the alignment while the Syarikat Pembenaan Yeoh Tiong Lay Sdn Bhd-TH Properties Sdn Bhd consortium (‘YTL-THP’) has been selected for the southern portion of the KL-SG HSR project alignment. The contracts will be awarded upon the satisfactory conclusion of negotiations between MyHSR Corp and MRCB Gamuda Consortium and YTL-THP consortia respectively.

The PDPs will be responsible for designing and delivering the civil works for the KL-SG HSR project at an agreed cost and schedule. It shall carry out all necessary activities throughout the planning, construction, testing, and commissioning phases, amongst others.

MyHSR Corp estimates that the KL-SG HSR project will comprise of 14.9km tunnels, out of its 335km HSR alignment within Malaysia. The tunnels are predominantly located in urban areas along the HSR alignment with approximately 8.8km bored tunnel and 6.1km mined tunnel.

 

“We are pleased to have selected two very capable consortia to work on the project. The PDPs will bring both local and international experience, through their own experience in building railways in the country and through partnerships with HSR experts, and together, we will build the KL-SG HSR project,” said Dato’ Mohd Nur Ismal bin Mohamed Kamal, Chief Executive Officer of MyHSR Corp. “We look forward to emulating the success of previous iconic projects in the country,” he added.

The PDP tender that was called on 22 November 2017 was conducted via an open tender by MyHSR Corp. The tender was open to parties with experience in railway design and construction, familiar with Malaysian Railway construction practices and regulatory requirements, as well as the Malaysian supply market conditions. The tender also promoted involvement of Malaysian firms consistent with the Government’s procurement objectives to stimulate and encourage the growth of local industries through optimal usage of local resources and materials.

The Kuala Lumpur-Singapore HSR is a strategic project between the Governments of Malaysia and Singapore that aims to facilitate a 90-minute travel time between Kuala Lumpur and Singapore. The project is expected to enhance business linkages and bring the people of both countries closer together. The iconic project includes domestic services within Malaysia that will improve intercity connectivity and promote economic agglomeration under the Socio- economic Development Programme (SEDP) intended to benefit local communities along the corridor.

The Governments of both countries signed a Bilateral Agreement on 13 December 2016, which captured the key points of agreement on the project, including the technical parameters, commercial model, customs, immigration and quarantine clearance, safety and security matters, regulatory framework and project management approach.

Eight stations are currently planned for the Kuala Lumpur–Singapore HSR: Bandar Malaysia, Sepang-Putrajaya, Seremban, Melaka, Muar, Batu Pahat and Iskandar Puteri stations in Malaysia and the Jurong East station in Singapore, with operations of the KL-SG HSR service between Kuala Lumpur and Singapore targeted for commencement by 31 December 2026.

MyHSR Corp is a company incorporated in 2015, wholly owned by the Minister of Finance Incorporated. As the Government of Malaysia’s project delivery vehicle for the Kuala Lumpur – Singapore HSR project, MyHSR Corp is responsible for the development and implementation of the project.

 

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

18/05/2022

Auckland Light Rail opens tender process

Auckland Light Rail opens tender process

The tender processes for the $14.6bn Auckland Light Rail and the Additional Waitematā Harbour Connections project have opened, marking an…

14/06/2022

Saudi’s NEOM awards drill and blast contracts

Saudi’s NEOM awards drill and blast contracts

Saudi’s futuristic NEOM city of the future project has awarded drill and blast tunnelling contracts – totalling 28km in length…

23/06/2022

Resilience on show at Philly’s NAT 2022 conference

Resilience on show at Philly’s NAT 2022 conference

Despite the raft of challenges facing the tunnelling industry, the mood at the North American Tunnelling (NAT) conference this week…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more