Home > Nepal’s first TBM hits impressive advance rates

Nepal’s first TBM hits impressive advance rates

Tris Thomas

Written by Tris Thomas on 30/07/2018 in News

Tagged: Robbins TBM

Nepal’s first TBM, a 5.06m diameter Robbins Double Shield, recently bored over 1,000m in one month and has been averaging an impressive 800m per month on the country’s Bheri Babai Diversion Multipurpose Project (BBDMP). The project is owned by the Government of Nepal’s Department of Irrigation (DOI) and operated by contractor China Overseas Engineering Group Co. Ltd. Nepal Branch (COVEC Nepal).

The decision to use a TBM, wich was supplied in summer 2017, was a departure for a nation where drill & blast has long been the preferred tunnelling method. Early studies done on the tunnel path predicted that drill & blast excavation of the 12.2km tunnel would take close to 12 years to complete. The tunnel is located in the Siwalik Range, part of the Southern Himalayan Mountains, where geology consists of mainly sandstone, mudstone, and conglomerate.

Mr. Wang Wu Shui, General Manager for COVEC Nepal, cited several factors that have contributed to the good advance rates so far, “In China, there is a proverb about TBM construction: ‘geology is the premise, equipment is the foundation, and talents are the key’. The great advance rates achieved at present mainly lie in preliminary planning, process control, and professional construction personnel.” Shui added that technical training and guidance are provided for each position so that all personnel can fully understand their job and team responsibilities. If unforeseen circumstances arise and there is no operator for a certain position, others have enough training to fill the role.

To ensure the best TBM performance and to prevent downtime, machine maintenance occurs daily at a fixed time. Geological engineers are sent to analyze the ground conditions twice daily so that construction personnel can adjust the tunneling parameters and prepare for auxiliary measures if geological changes are predicted.

The ground conditions during the record-setting month consisted mainly of sandstone and mudstone, but that is set to change. At about the 5.8km mark, the machine will encounter a major fault zone known as the Bheri Thrust. Clay and water ingress are expected throughout the fault, which is about 400 to 600m wide.

COVEC Nepal are prepared for the conditions and have worked out efficient tunneling logistics to decrease downtime. “The two working procedures of tunneling and segment erection are carried out simultaneously under the double shield tunneling mode, and the time to erect a ring of segments is 15 minutes in general,” said Shui. “Under the single shield tunnelling mode, segment erection comes after tunnelling in a sequential process, but the segment erection time is still about 15 minutes.” To further reduce time, consolidation grouting is carried out in advance during daily maintenance to avoid the impact of downtime for grouting on the overall construction progress.

Once complete, the BBDMP will irrigate 60,000 hectares of land in the southern region of Nepal, and benefit an estimated 30,000 households. It will divert 40 cubic meters of water per second from Bheri River to Babai River under a head of 150m using a 15m tall dam, providing year-round irrigation in the surrounding Banke and Bardia districts. The water will also be used for hydroelectricity, with a generating capacity of 48MW benefiting the country with US$20M annually. The initial success of the TBM operation has already inspired developers and contractors to opt for TBMs over conventional excavation methods on upcoming Nepalese tunnels.

 

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

13/12/2022

RFQ soon for Hudson Tunnel Project Delivery Partner (PDP)

RFQ soon for Hudson Tunnel Project Delivery Partner (PDP)

The Gateway Development Commission (GDC) has announced that it will release a Request for Qualifications (RFQ) for a Project Delivery…

05/12/2022

ITA Awards 2022 goes live tomorrow

ITA Awards 2022 goes live tomorrow

The ITA Tunnelling and Underground Space Awards goes live tomorrow as a digital event running from 6th December to 8thDecember,…

31/10/2022

EPBMS delivered for Ninth Bangkok Water Supply Tunnel

EPBMS delivered for Ninth Bangkok Water Supply Tunnel

TERRATEC has celebrated the successful Factory Acceptance Tests of two new 4.39m diameter EPBMs and one 4.8m diameter EPBM destined…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more