The Chennai Metro Rail Limited (CMRL) has issued invitation to bids for two contract packages on Line 4 of the Chennai Metro which total in the region of 10km of twin-bore tunnel and eight underground stations.
Firstly Package C4-UG-01/2021, featuring some 5km of twin-bore tunnel and four underground stations, and Package C4-UG-02/2021, comprising a further 5km of twin-bore tunnel and four more underground stations.
The deadline for submission for both is 18th June 2021, at 15:00Hrs, with both having a contract duration of 48 months.
There will be a Pre-bid Meeting for Package C4-UG-01/2021 on 6th April 2021 at 11.00hrs. (IST), and for Package C4-UG-02/2021later the same day, at 15:00hrs (IST).
For more details, interested bidders may contact Mr. Gurunath Reddy, Addl. General Manager (Contract Procurement), Chennai Metro Rail Limited, Room No. 507, Administrative Building, CMRL Depot, Poonamallee High Road, Koyambedu, Chennai – 600107, Tamil Nadu, India.
Comments: