tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2023
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Second Avenue Subway Phase 2 advances procurement

Second Avenue Subway Phase 2 advances procurement

Tris Thomas

Written by Tris Thomas on 06/07/2023 in News

Tagged: Second Avenue Subway

New York State Governor Kathy Hochul announced on 5th July that the Metropolitan Transportation Authority is advancing on Phase 2 of the Second Avenue Subway with the solicitation of the first contract for construction of the future extension of the Second Avenue Subway to 125th Street in Harlem.

Screenshot 2023 07 12 at 13.11.23

The long-awaited extension will deliver transportation equity to East Harlem, one of the most transit-dependent neighborhoods in New York City. As part of this announcement, the MTA also unveiled new conceptual renderings of the proposed stations for the extension, providing future riders with a first-ever glimpse into the potential station interior and exterior designs. The draft renderings are subject to further design development and are available here.

“As part of my administration’s efforts to advance transit equity across New York State, the Second Avenue Subway project will expand critical public transportation service to East Harlem, creating more opportunity for residents,” Governor Hochul said. “We remain committed to keeping this long-envisioned project moving along swiftly for East Harlem, and I am proud to see it moving one step closer to reality.”

The scope of work for the first contract for Second Avenue Subway Phase 2 incorporates lessons learned from Phase 1 and will involve critical utility relocation, laying the groundwork for advancing construction of three future stations and necessary system infrastructure. The contract will be solicited as a Design-Bid-Build A+B contract, which incentivizes proposers to compete on both cost and time needed to complete the work. In 2022, MTA Construction and Development saved more than $100M on A+B contract awards compared to estimates. The solicitation has been posted, and a contract is expected to be awarded this fall, with work to begin by the end of the year.

Additional cost containment initiatives in Phase 2 include reuse of a tunnel segment that was built in the 1970s from 110 Street to 120 Street along Second Avenue, early real estate acquisition, adoption of best value contract structures like A+B contracts, reduction in back-of-house and ancillary space, and close coordination of contracts.

The second phase of the project will extend Q train service from 96 Street north to 125 Street and then west on 125 Street to Park Avenue, approximately 2.4km (1.5 miles) in total. There will be two new stations at 106 Street and 116 Street on Second Ave, and a direct passenger connection with the existing 125 Street subway station on the Lexington Avenue subway line. Phase 2 will also feature an entrance at Park Avenue to allow convenient transfers to the Metro-North Railroad 125 Street Station.

Each station will have above-ground ancillary buildings that house ventilation, mechanical, and electrical equipment, as well as space for possible ground-floor retail and community uses. The expansion will serve an additional 100,000 daily riders and provide three new ADA accessible stations — raising the bar for customer comfort and convenience. Increased multimodal transit connectivity at the 125 Street station at Park Avenue with connections to the 456, Metro-North trains and the M60 Select Bus Service to LaGuardia Airport, will allow for convenient transfers to other subway and commuter rail lines, facilitating smoother, faster transportation across the city and metropolitan region.

Phase 1 of the project extended the Q line from 63 Street to 96 Street and was New York City’s largest expansion of the subway system in 50 years. Service opened on January 1, 2017, with additional stations at 72 Street and 86 Street. Since its completion, the Second Avenue Subway has carried more than 130 million passengers in total, including more than 200,000 passengers on a typical pre-pandemic day.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

12/07/2023

Casting starts for Fehmarnbelt immersed tube tunnel

Casting starts for Fehmarnbelt immersed tube tunnel

Casting of the tunnel elements for the 18km Fehmarnbelt Immersed Tunnel between Lolland in Denmark and Puttgarden on the German…

17/07/2023

EPBM launched on Turkey’s Halkali-Ispartakule rail project

EPBM launched on Turkey’s Halkali-Ispartakule rail project

July 11, 2023, saw the 8.54m diameter “CREC 1148” EPBM designed and manufactured by China Railway Engineering Equipment Group Co….

08/09/2023

Sydney Northern Beaches Tunnel project scrapped

Sydney Northern Beaches Tunnel project scrapped

The New South Wales Government has today confirmed the decision to cancel the Beaches Link project. The Beaches Link project…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more