Société du Grand Paris has awarded the construction contract for works package 1 of Line 18 of Grand Paris Express, the biggest urban mobility programme currently under way in Europe, to the joint venture led by VINCI Construction Grands Projets. This first section will link Orly airport to Massy-Palaiseau; Line 18 will then be extended to Versailles.
Worth €799M, of which 20% reserved for SMEs, the contract calls for digging 11.8km of tunnels using two TBMs, and building three stations (Antonypôle, Massy Opéra and Massy-Palaiseau), 13 ancillary engineering structures, 10 branches connecting with the tunnel, and 850m of cut and cover. In total, more than 1 million cubic metres of material will be excavated.
At its peak, the contract will employ up to 700 people (500 labourers and 200 supervisory staff). Over the 83-month duration of the worksite, it will also create the equivalent of 148 full-time jobs for people in social integration programmes.
In addition, the VINCI Group has established an endowment fund, Chantiers et Territoires Solidaires, to support non-profit entity initiatives relating to employment and the social fabric of communities located close to Grand Paris Express projects.
As part of the Grand Paris Express programme, the consortium is currently executing, on Line 15 South, the works packages between Fort d’Issy-Vanves-Clamart and Villejuif Louis Aragon, as well as the Noisy-Champs station works package, and is responsible for extending Line 14 South towards Orly. The VINCI Group is also working on other Grand Paris Express works packages through specialist activity subsidiaries of VINCI Construction, Eurovia (for laying rail track) and VINCI Energies.