tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Canadian Tunnelling
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2024
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > HS2 launches third Northolt Tunnel TBM

HS2 launches third Northolt Tunnel TBM

Written by Tris Thomas on 25/02/2024 in News

Tagged: Costain,Herrenknecht,HS2,Skanska,Strabag

HS2’s London tunnels programme has passed another major milestone following the launch of the section’s third TBM. Herrenknecht 9.11m diameter EPBM Emily will be used to dig almost half of the 13.5km Northolt Tunnel through London Clay.

She will bore 5.4km under Ealing from Victoria Road Crossover Box, near HS2’s new Old Oak Common station, to Greenpark Way in Greenford.

41d566e8d93a47f197db52cb27be1493

HS2’s London Tunnels contractor, Skanska Costain STRABAG joint venture, assembled the TBM underground at the Victoria Road site after being lifted in parts and lowered into a shaft.

Speaking about the next TBM launching in London for HS2, Malcolm Codling, project Client Director, HS2 Ltd, said: “We are working at peak construction on HS2, delivering the tunnels which HS2 trains will travel through under London. The preparation to launch TBM Emily has been complex and we remain on schedule to complete the Northolt Tunnel in 2025.”

The Northolt Tunnel will carry HS2 trains in and out of London – extending between the new Old Oak Common superhub and the outskirts of the capital at West Ruislip.

The twin-bore tunnel is being built in two sections. Two TBMs, named Sushila and Caroline, are already constructing it eastward between West Ruislip and Greenford. Another two – Emily and Anne – are being used to dig the tunnel in the opposite direction from Victoria Road Crossover Box to Greenford.

Emily and Anne’s tunnel drive will cover 5.4km of the tunnel in total – slightly less than those being used on the other section. Anne – the fourth and final Northolt TBM – will launch next month.

The quartet of TBMs are all set to complete their journeys in 2025, when they will be extracted from the ground through giant shafts at Greenpark Way.

The London Clay, that will be extracted to build the tunnel, will be taken away from Victoria Road Crossover Box by conveyor, and taken to the London Logistics Hub at Willesden Euro Terminal. From there, it will be taken by rail and reused at sites in Cambridgeshire, Kent and Rugby.

James Richardson, Managing Director of Skanska Costain STRABAG joint venture (SCS JV), said: “The HS2 London Tunnels team are well on the way to delivering a new railway into the heart of London with the launch of TBM Emily. Next month, we will be launching TBM Anne who together with Emily will form the tunnel from old Oak Common to Greenpark Way Shaft where they will meet with TBMs Sushila and Caroline, who are already halfway to completing their journeys from West Ruislip.”

HS2 is also making progress on preparations on the separate tunnel between Old Oak Common and Euston – the line’s ultimate central London terminus.

The Atlas Road Logistics Tunnel breakthrough in January. The logistics tunnel is runs from the Old Oak Common Station box to Atlas Road logistics site and will facilitate the tunnelling operation to construct the Euston Tunnel.

Two further TBMs will be delivered to Old Oak Common later this year, and placed into the underground box, ready to begin boring the Euston Tunnel. Following the Government’s Network North announcement in October last year, the funding and delivery arrangements for the Euston Tunnel are being reviewed.

Herrenknecht

Pioneering Underground Technologies - Herrenknecht AG is the technology and market leader in mechanized tunnelling. As the only company worldwide, Herrenknecht delivers cutting-edge tunnel boring machines for all ground conditions and in all diameters - ranging from 0.10 to 19 meters.

More Information | info@herrenknecht.com | +49 7824 3020

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

21/05/2025

Hudson Yards Concrete Casing – Section 3 reaches milestone

Hudson Yards Concrete Casing – Section 3 reaches milestone

New York’s Gateway Development Commission (GDC) has announced that the Hudson Yards Concrete Casing – Section 3 (HYCC-3) Project ismore…

04/03/2025

NSW sets up silica health risk Taskforce

NSW sets up silica health risk Taskforce

The New South Wales (NSW) Minns Labor Government has established a new Expert Taskforce to oversee and help address silica…

21/01/2025

Herrenknecht delivers E-Power Pipe machine

Herrenknecht delivers E-Power Pipe machine

December saw Herrenknecht hand over an E-Power Pipe machine to Heitkamp Construction Swiss GmbH for use – among other projects…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social

Facebook Linkedin X-twitter Instagram
Youtube Soundcloud Linkedin Rounded Border Svgrepo Com White

Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.Ok