tunnelling-journal (1)
tunnelling-journal (1)
  • Home
  • Print
    • Subscribe
    • Tunnelling Journal
    • Breakthrough
    • ITA Activity Report
    • A&NZ Journal
    • WTC Preview
    • Media Kit
  • Digital
    • Newsletter
    • E-Shots
    • TJ Digital edition
    • Products Page
    • Media Kit
  • Conferences
    • BTS Conference and Exhibition
    • Cutting Edge 2022
  • Buyer’s Guide
  • Events Diary
  • Jobs
  • About Us
  • Contact Us
  • Podcast

Home > Tight radius success in Bangkok

Tight radius success in Bangkok

Tris Thomas

Written by Tris Thomas on 02/11/2017 in News

Tagged:

On September 22, 2017, a TERRATEC Tight Radius Shield successfully completed a challenging drive for the Bangkok Metropolitan Electricity Authority’s (MEA) Phra Khanong Cable Tunnel Project, in Bangkok, Thailand. The 3.20m diameter TERRATEC S48 EPBM, being operated by Thai contractor Nawarat Patanakarn PCL, excavated a sharp 32m-radius curve as it exited the project’s launch shaft to negotiate the piles of an adjacent expressway ramp.

To achieve this challenging curved alignment, the EPBM was manufactured with an extreme X-type articulation system that provides a maximum articulation angle of 6.6-degrees. “The TBM was specifically designed to cope with small radius curves,” said Mr Pakpong Phongsaisri, Project Engineer for Nawarat Patanakarn. “It is a highly efficient machine and has done an excellent job in difficult conditions.”

Designed to accommodate a new high-voltage cable system, the Phra Khanong Cable Tunnel Project is the first of a series of planned tunnelling projects by the MEA that are being built to meet increased power demands in the Thai capital.

Located at the intersection of the Phra Khanong canal and Sukhumvit Road the project is situated in one of the busiest areas of downtown Bangkok and is subject to tight alignment constraints. The TBM was launched on its first, 495m long, drive in early February from a 7m diameter shaft located beneath an elevated expressway ramp with limited working head room. Due to the presence of the expressway piles, the TBM was required to embark on a sharp 32m-radius curve immediately upon exiting the shaft.

Tunnelling operations were closely observed throughout the manoeuvre via a settlement monitoring programme that demonstrated minimal impact on the existing above ground structures. As the machine progressed through the curve it installed a tunnel lining of short 300mm wide x 125mm thick steel sets, before transitioning to 1.1m wide x 225mm thick traditional tapered precast concrete segments (left/right/straight).

Featuring a classic soft ground open spoke cutterhead design, with knife bits to assist break-in and break-out of the steel fibre reinforced concrete shaft eyes, the EPB machine has coped extremely well with the geological conditions along the alignment, which consist of fine sands and stiff clays with a groundwater head of about 2 bars.

Prior to the TBM’s breakthrough last month, the machine completed a second, 30m long 99m-radius, curve on its approach to the reception shaft, which was handled with ease.

Since then, the TBM has been retrieved and is currently being prepared for its second, 293m-long, drive from the central launch shaft, which will commence in mid-November. Once again, the TBM will launch into a tight curve, this time with a 43.7m-radus on a 2% up-grade trajectory, passing under the Phra Khanong canal and heading northwards to a second retrieval shaft.

Throughout the duration of the project, machine operation is being assisted at all times by TERRATEC’s highly-experienced Field Service team. “We are extremely pleased with the service and support offered by the Terratec team and are looking forward to successful completion of the tunnelling works in the coming months,” says Phongsaisri.

Comments:

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search

Digital Edition

More Like This

04/11/2022

LHDA awards Polihali Transfer Tunnel and Dam contracts

LHDA awards Polihali Transfer Tunnel and Dam contracts

The Lesotho Highlands Development Authority (LHDA) has announced the Polihali Transfer Tunnel and Polihali Dam construction contract awards, the two…

28/11/2022

Final tunnelling contract awarded on Sydney Metro West

Final tunnelling contract awarded on Sydney Metro West

John Holland, CPB Contractors (CPB) and Ghella joint venture (JCG JV) has been awarded the Eastern Tunnelling contract to deliver…

12/01/2023

Get serious about silicosis, says UK parliamentary report

Get serious about silicosis, says UK parliamentary report

The UK’s All Party Parliamentary Group (APPG) for Respiratory Health has just published a new report on silicosis.  Improving Silicosis…

  • Contact Us
  • Media Kit
  • Magazine Archive

Newsletter

The latest from the Tunneling Journal direct to your inbox.

Social



Enquiries

TGS Media Ltd
The Old Library
Webster House
Dudley Road
Tunbridge Wells
TN1 1LE
United Kingdom

© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkRead more